Referred to: The Economic Development, Tourism, Housing, Planning and Transit
Committee (Chairman James Maloney and Legislators Archer, Delaune, Litts, Maio,
Rodriguez, and Woltman), and The Ways and Means Committee (Chairman
Gerentine and Legislators Archer, Bartels, Lopez, James Maloney, Joseph Maloney,
and Petit)
Chairman of the Economic Development, Tourism, Housing, Planning, and Transit
Committee, James F. Maloney, offers the following:
WHEREAS, this resolution has been submitted by the County Executive on
behalf of the Department of Planning; and
WHEREAS, Ulster County Resolution No. 319 of October 11, 2001
established a County policy requiring the Purchasing Director and relevant
department head to explore the use of a Project Labor Agreement (“PLA”) for certain
construction projects; and
WHEREAS, Ulster County Resolution No. 374 of December 19, 2017
amended the prior policy under Resolution No. 319 thereby requiring the Purchasing
Director and appropriate County department head to initiate a Due Diligence Study
(“DDS”) to explore and consider using a PLA to reduce construction costs and avoid
delay claims and potential litigation for all construction projects in which the
individual project is equal to or exceeds $5,000,000 and the project requires the
services of three or more contractors for completion, and upon completion of the
DDS, the findings of said study and the recommendation of the Purchasing Director
and appropriate Department Head shall be filed with the Clerk of the Legislature; and
WHEREAS, the Ashokan Rail Trail Project- Phase 2 Construction- Capital
Project No. 459 (the “Project”), has an estimated budget that exceeds $5,000,000,
and the Project will require the services of three or more contractors for completion,
which requires the Director of Purchasing and Director of Planning to initiate a DDS
for the Project; and
WHEREAS, a DDS was initiated by the County and conducted by Seeler
Engineering, P.C., which projects that utilization of a PLA for the Project will result
in direct labor cost savings of $167,200, approximately 7.4 percent of estimated labor
costs, and will best serve Ulster County’s interest in obtaining the best work at the
lowest possible price, preventing favoritism, fraud and corruption, and gaining
measurable management flexibility and benefits and promoting other public interests
including avoidance of delays and local labor unrest; and
WHEREAS, based on careful review and consideration of the findings and
recommendation of the DDS, the Director of Purchasing and Director of Planning
recommend that a Project Labor Agreement be made part of the Project, subject to
the review and ratification by the Ulster County Legislature; and
WHEREAS, the Ulster County Legislature has reviewed the DDS as filed
with the Clerk of the Legislature; now, therefore be it
RESOLVED, that the Ulster County Legislature hereby ratifies the
recommendation of the Director of Planning and Director of Purchasing to use a
Project Labor Agreement for the Ashokan Rail Trail Project- Phase 2 ConstructionCapital Project No. 459 based on projected labor costs savings and non-economic
benefits contributing to the success of the Project,
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: 17 NOES: 4
(Noes: Legislators Greene, Joseph Maloney, Petit,
and Wawro)
(Absent: Legislators Eckert and Maio)
Passed Committee: Economic Development, Tourism, Housing, Planning, and
Transit on April 3, 2018
Passed Committee: Ways and Means on April 10, 2018
FINANCIAL IMPACT:
PROJECTED CAPITAL PROJECT SAVINGS- $167,200.00
STATE OF NEW YORK
ss:
COUNTY OF ULSTER
I, the undersigned Clerk of the Legislature of the County of Ulster, hereby certify that the foregoing resolution is
the original resolution adopted by the Ulster County Legislature on the 17th Day of April in the year Two Thousand and
Eighteen, and said resolution shall remain on file in the office of said clerk.
IN WITNESS WHEREOF, I have hereunto set my hand and seal of the County of Ulster this 18th Day of April in
the year Two Thousand and Eighteen.
|s| Victoria A. Fabella
Victoria A. Fabella, Clerk
Ulster County Legislature
Submitted to the County Executive this Approved by the County Executive this
18th Day of April, 2018. 18th Day of April, 2018.
|s| Victoria A. Fabella |s| Michael P. Hein
Victoria A. Fabella, Clerk Michael P. Hein, County Executive
Ulster County Legislature
Current Text: PDF
Updated: February 1, 2019
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 138
Committee Vote to Adopt Resolution No. 138
Committee Vote to Adopt Resolution No. 138
...