Referred to: The Public Works, Capital Projects and Transportation Committee (Chair Nolan and Legislators Donaldson, Kovacs, Litts, and McCollough), and The Ways and Means Committee (Chairman Gavaris and Legislators Collins, Hansut, Kovacs, Nolan, and Roberts)
Chair of the Public Works, Capital Projects and Transportation Committee, Kathy Nolan, and Deputy Chair Herbert Litts, III offer the following:
WHEREAS, this resolution has been submitted at the request of the County Executive on behalf of the Department of Public Works; and
WHEREAS, Capital Project No. 585 for Bridge Substructure Repairs was established pursuant to Resolution No. 72 dated February 16, 2021, in the amount of $66,000.00 for design services for the Rosendale Bridge (BIN 3347460) in the Town of Rosendale, Conyes Bridge (BIN 3346910) in the Town of Saugerties and Leggs Mills Bridge (BIN 3347530) in the Town of Saugerties; and
WHEREAS, Capital Project No. 585 for Bridge Substructure Repairs was further amended pursuant to Resolution No. 548 dated November 15, 2022, in the amount of $212,502.00 for additional design services and construction inspection services; and
WHEREAS, Capital Project No. 585 for Bridge Substructure Repairs was further amended pursuant to Resolution No. 179 dated April 18, 2023, for additional construction services in the amount of $118,275.00; and
WHEREAS, Capital Project No. 585 for Bridge Substructure Repairs was further amended pursuant to Resolution No. 659 dated November 14, 2023, in the amount of $ 4,350,000.00 for construction services; and
WHEREAS, Capital Project No. 585 for Bridge Substructure Repairs was further amended pursuant to Resolution No. 537 dated October 15, 2024, in the amount of $75,000.00 for construction services; and
WHEREAS, the Leggs Mills Bridge rehabilitation construction project on County Road 31, in the Town of Ulster includes the replacement of the concrete bridge deck, localized steel painting and substructure repairs, among other items in accordance with the plans as per RFB-UC23-146C; and
WHEREAS, the Rosendale Bridge rehabilitation construction project on Keator Avenue, in the Town of Rosendale includes the replacement of the bridge bearings and substructure repairs of a two-span steel girder bridge, among other items in accordance with the plans as per RFB-UC23-147C; and
WHEREAS, unforeseen conditions uncovered during construction including steel repairs, joint replacements and scour repairs required additional permitting and construction inspection hours during construction necessitating additional funding in the amount of $90,000.00; and
WHEREAS, the Commissioner of Public Works requests that Capital Project No. 585 be amended to increase the funding available for construction services for Rosendale Bridge in the amount of $90,000.00for a total project cost of $4,911,777.00; now, therefore be it
RESOLVED, based upon examination by the Ulster County Legislature, the County’s funding of this Project constitutes a Type II action as defined under Section 4.5.5 of the County of Ulster’s State Environmental Quality Review Act (SEQRA) Type II List, which was adopted pursuant to Resolution No. 118 dated April 20, 2010; and
RESOLVED, Ulster County has determined that this funding action does not pose a significant potential environmental impact and may be progressed as a Type II action in accordance with 6 NYCRR Part 617 of SEQRA, and does not require any further determination or procedure under SEQRA; and
RESOLVED, that Capital Project No. 585 for Bridge Substructure Repairs be amended as follows:
INCREASE AMOUNT
Capital Project No. 585 Substructure Repairs $90,000.00
Rosendale Bridge
Leggs Mills Road Bridge
and, be it further
RESOLVED, that the 2025 Ulster County Capital Fund budget is hereby amended as follows:
INCREASE AMOUNT
HH.5197.0585-4300.4505 Capital Project No. 585 $90,000.00
(App. #) Construction Inspection Services
HH.5197.0585-3500.5710 Revenue- Serial Bonds $90,000.00
(Rev. #),
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: NOES:
Passed Committee: Public Works, Capital Projects and Transportation on ____________.
Passed Committee: Ways and Means on ____________.
FINANCIAL IMPACT:
$90,000.00 – COUNTY CAPITAL FUND APPROPRIATIONS
$90,000.00 – COUNTY REVENUE SERIAL BONDS
***A BOND RESOLUTION WILL BE REQUIRED***