Resolution Information
RESOLUTION TEXT +-
Referred to: The Economic Development, Planning, Education, Employment, Arts and Agriculture Committee (Chairwoman Sperry and Legislators Clinton, Corcoran, Hewitt, Litts, Stewart and Walls), The Public Works, Capital Projects and Transportation Committee (Chair Nolan and Legislators Donaldson, Kovacs, Litts, and McCollough), and The Ways and Means Committee (Chairman Gavaris and Legislators Collins, Hansut, Kovacs, Nolan, and Roberts)
Chairwoman of the Economic Development, Planning, Education, Employment, Arts and Agriculture Committee, Megan Sperry, and Deputy Chair Herbert Litts, III offer the following:
WHEREAS, this resolution has been submitted at the request of the County Executive on behalf of SUNY Ulster; and
WHEREAS, Resolution No. 547, dated December 20, 2016 approved the establishment and funding of Capital Project No. 489 SUNY Ulster - Dewitt Library Roof Replacement in the amount of $250,000.00; and
WHEREAS, Resolution No. 111, dated March 20, 2018, amended Resolution No. 547 that established Capital Project No. 489 SUNY Ulster - Dewitt Library Roof Replacement – to change the scope of such Capital Project to include roof assessments and design services for various buildings - SUNY Ulster; and
WHEREAS, Resolution No. 259, dated June 19, 2018, authorized the Chair of The Ulster County Legislature to Enter into an agreement with the New York State Dormitory Authority of The State of New York (DASNY) for project management services – Ulster County Community College; and
WHEREAS, Resolution No. 463, dated November 20, 2018, approved the Work Order Number 2019-003 totaling $116,000.00 (inclusive of DASNY in-house design fee of $116,000.00) for in-house design services to design roof replacements for John Vanderlyn Hall Skylight, MacDonald Dewitt Library and Burroughs Hall (Lecture Hall); and
WHEREAS, Resolution No. 147, dated April 16, 2019, approved the Work Order Number 2019-005 totaling $1,407,000.00 (inclusive of DASNY Construction Fee of $97,000.00) for construction phase services related to roof replacements of John Vanderlyn Hall Skylight, MacDonald Dewitt Library and Burroughs Hall (Lecture Hall); and
WHEREAS, the Resolution No. 302, dated July 16, 2019, approved the Work Order Number 2019-009 totaling $1,600,000.00 (inclusive of DASNY Design Fee of $104,500.00 and DASNY Construction Fee of $140,000.00) for design and construction phase services of Campus Roofs Project – Hardenbergh Hall; and
WHEREAS, the Resolution No. 99, dated March 16, 2021 approved an increase in funding in the amount of $2,448,000.00 for design, testing and construction services of Phase 3, Campus Roof Project for Hasbrouck Hall and Exterior Emergency Façade Renovations of falling fascia stone at multiple buildings on campus; and
WHEREAS, the Resolution No. 300, dated July 20, 2021 approved Work Order 2019-009A totaling $1,535,000.00 (inclusive of DASNY Design Fee of $182,347.00 and DASNY Construction Fee of $270,395.00) to address the emergency needs of the failing fascia stone at Dewitt Library and Senate Gymnasium Roof Feasibility Study; and
WHEREAS, the Ulster County Legislature via Resolution No. 474 dated October 19, 2021 approved the Work Order No. 2019-009B in the amount of $500,000.00 for emergency roof work services of the Campus Roof Capital Project; and
WHEREAS, the Resolution No. 626, dated December 19, 2022 approved Work Order 2019-009C totaling $2,402,331.00 (inclusive of DASNY fee in the amount of $170,282.00) for the design, testing and construction phase services for Student Live Center Roof; and
WHEREAS, it is now necessary to fund the design, testing and construction of the Burroughs Hall Roof, including the building’s HVAC system, related to the Capital Project No. 489 SUNY Ulster – The Campus Roofs Capital Project; and
WHEREAS, the approved 2024-2029 Capital Improvement Program included the Roof Replacement and Exterior Site Work capital projects; and
WHEREAS, DASNY provided a Work Order Number 2019-009D that is needed in funding for the design, testing and construction of the Burroughs Hall Roof capital project; and
WHEREAS, such Work Order totals $6,820,884.00 (inclusive of DASNY Design Fee in the amount of $433,751.00) which will be divided as follows: $3,410,442.00 State and $3,410,442.00 Ulster County; and
WHEREAS, SUNY Ulster Board of Trustees approved the Work Order 2019-009D with the Dormitory Authority of the State of New York (Capital Project: Campus Roofs Project) via Resolution No. 24-08-31; now, therefore be it
RESOLVED, that the Ulster County Legislature hereby approves the Work Order 2019-009D with DASNY – Design, Testing and Construction Phase Services for Burroughs Hall Roof, including the building’s HVAC system, related to the Campus Roofs Capital Project No. 489 – Campus Roofs - SUNY Ulster; and, be it further
RESOLVED, that Capital Project Nos. 489 is hereby amended as follows;
INCREASE AMOUNT
Capital Project No. 489 SUNY Campus Roofs $6,820,884.00
and, be it further
RESOLVED, that the 2024 Ulster County Capital Fund Budget is hereby amended as follows:
INCREASE AMOUNT
HH.2497.0489-2300.2550 Other Equipment & $6,820,884.00
(App.#) Capital Outlays Construction
HH.2497.0489-3500.5710 Revenue – Serial Bonds $6,820,884.00
(Rev.#),
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: NOES:
Passed Committee: Economic Development, Planning, Education, Employment, Arts and Agriculture on _____________.
Passed Committee: Public Works, Capital Projects and Transportation on _____________.
Passed Committee: Ways and Means on _____________.
FINANCIAL IMPACT:
$6,820,884.00 – CAPITAL PROJECT NO. 489 APPROPRATIONS
$6,820,884.00 – COUNTY REVENUE - SERIAL BONDS
(50% REIMBURSABLE FROM NYS DORMITORY AUTHORITY)
*** A BOND RESOLUTION WILL BE REQUIRED ***
Current Text: PDF
Updated: September 3, 2024
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 450
Committee Vote to Adopt Resolution No. 450
Committee Vote to Adopt Resolution No. 450
Committee Vote to Adopt Resolution No. 450
...