Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works and Capital Projects Committee (Chairwoman Petit and Legislators Fabiano, Greene, Litts, and Nolan), The Legislative Programs, Education and Community Services Committee (Chairman Delaune and Legislators Collins, Donaldson, Haynes, and Wawro), and The Ways and Means Committee (Chairwoman Archer and Legislators Gerentine, Maio, Joseph Maloney, Petit, Rodriguez, and Ronk)
Chairman of the Legislative Programs, Education and Community Services Committee, James Delaune, and Deputy Chair Heidi Haynes, offer the following:
WHEREAS, the resolution has been submitted by the County Executive on behalf of the Ulster County Community College (“UCCC”); and
WHEREAS, Resolution No. 441 of 2016 established Capital Project No. 486 Window Replacement Project and amended the 2016-2021 Capital Improvement Program to add such project and fund such project in the amount of $668,000.00; and
WHEREAS, the Resolution No. 259 of 2018 authorized the Chair of the Ulster County Legislature to enter into an agreement with the Dormitory Authority of the State of New York (“DASNY”) for project management services; and
WHEREAS, the Resolution No. 107 of 2019 approved the Work Order with DASNY in the amount of $600,400.00 (inclusive of DASNY fee of $74,300.00) for Phase-1 of Window Replacement Project Jacob Hardenbergh Hall; and
WHEREAS, the Phase-1 Window Replacement plan included the replacement of half of the windows in Hardenbergh Hall; and
WHEREAS, due to the poor condition of the windows in the Hardenbergh Hall and the necessary hazardous materials abatement project, it is now recommended that UCCC replace all windows within Hardenbergh Hall; and
WHEREAS, due to this increase in scope and necessary hazardous materials abatement, it is necessary to increase such total project funding to $1,120,000.00, an increase of $452,000.00; and
WHEREAS, SUNY Ulster Board of Trustees approved the Work Order with the Dormitory Authority of the State of New York (Capital Project: Window Replacement Project) via resolution #19-08-159; and
WHEREAS, such Work Order totals $519,600.00 (inclusive of DASNY Fee of $33,000.00) for such project, which will be divided as follows: $259,800.00 State and $259,800.00 Ulster County; now, therefore, be it
RESOLVED, the Ulster County Legislature hereby approves the execution of Work Order No. 2019-001A – Window Replacement Project with DASNY for the provision of providing design management services of a DASNY term consultant for design services and use DASNY staff to manage construction for the increased scope of Window Replacement project for Jacob Hardenbergh Hall; and, be it further,
RESOLVED, that the 2019 Ulster County Capital Fund Budget is hereby amended as follows:
INCREASE AMOUNT
HH.2497.0486.2300.2500 Equipment $452,000.00
(App. #)
HH.2497.0486.3500.5710 Serial Bonds $452,000.00
(Rev. #)
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: NOES:
Passed Committee: Public Health and Social Services on ____________.
Passed Committee: Legislative Programs, Education and Community Services on ____________.
Passed Committee: Ways and Means on ____________.
FINANCIAL IMPACT:
$452,000 – ADDITIONAL CAPITAL PROJECT NO. 486 APPROPRIATIONS
$452,000 – ADDITIONAL CAPITAL PROJECT NO. 486 SERIAL BONDS
AUTHORIZED (50% REIMBURSABLE FROM NEW YORK STATE
DORMITORY AUTHORITY)
***A BOND RESOLUTION WILL BE REQUIRED***
Current Text: PDF
Updated: October 21, 2019
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 387
Committee Vote to Adopt Resolution No. 387
Committee Vote to Adopt Resolution No. 387
Committee Vote to Adopt Resolution No. 387
...