Resolution No. 372

Amending Capital Project No. 507, Horsenden Pavement Overlay, For Anticipated Engineering Costs – Amending The 2018 – 2023 Capital Improvement Program – Department Of Public Works (Highways And Bridges)

Resolution Information

Status: 
Adopted

RESOLUTION TEXT +-

Print

Referred to: The Public Works and Capital Projects Committee (Chairman Fabiano

and Legislators Greene, Litts, Nolan, and Roberts), and The Ways and Means

Committee (Chairman Gerentine and Legislators Archer, Bartels, Lopez, Maio,

James Maloney, Joseph Maloney, and Petit)

Chairman of the Public Works and Capital Projects Committee, Dean J. Fabiano,

offers the following:

WHEREAS, this resolution has been submitted by the County Executive on

behalf of the Department of Public Works – (Highways & Bridges); and

WHEREAS, a project for Horsenden Pavement Overlay, in the Town of New

Paltz, PIN 8761.93 may be eligible for funding under Title 23 U.S. Code, as

amended, that calls for the apportionment of the costs of such program to be borne at

the ration of 80% federal funds 20% non-federal funds; and

WHEREAS, Capital Project No. 507 was established pursuant to Resolution

No. 309, dated July 18, 2017, in an amount of $13,000 to provide authorization and

funding for preliminary engineering and right-of-way incidental work; and

WHEREAS, Resolution No. 269 dated June 19, 2018 amended such capital

project for the additional preliminary engineering, Right-of-Way Work and for the

Project in the amount of $80,000.00, of which such costs may be reimbursable up to

80% with federal funds, bringing the total project cost to $93,000.00; and

WHEREAS, due to the scope of such projects, it is now necessary to increase

the total cost of Capital Project No. 507, to fund anticipated additional engineering

costs due to additional in house work in the scoping phase of the projects; and

WHEREAS, the project was approved by the Ulster County Transportation

Council in the 2018-2022 Transportation Improvement Program; and

WHEREAS, the County desires to advance the Project by making a

commitment of 100% of the non-federal share of the additional preliminary

engineering work; now

THEREFORE, the Ulster County Legislature, duly convened, it is hereby

 

RESOLVED, that the Ulster County Legislature hereby authorizes Ulster

County to pay in the first instance 100% of the federal and non-federal share of the

cost of engineering work for the Project or portions thereof; and, be it further 

 

RESOLVED, that, as funded, the Project is a Type II Action as defined under

6 NYCRR 617.5(c) (18) and does not require any determination or procedure under

the State Environmental Quality Review Act (SEQRA) and, be it further

RESOLVED, that the Ulster County Legislature has determined, after review

of the criteria contained in 6 NYCRR Parts 617.4 and 617.5, that the construction of

the project will constitute an Unlisted Action; and the County will conduct a

coordinated review and circulate its Notice of Intent to serve as Lead Agency,

together with the EAF and accompanying documentation to all interested and

involved agencies pursuant to 6 NYCRR Part 617.6(b) (2) (i) and 6 NYCRR Part

617.6(b) (3); and, be it further

RESOLVED, that in the event the full federal and non-federal share costs of

the Project exceeds the amount appropriated above, the Ulster County Legislature

shall convene as soon as possible to appropriate said excess amount immediately

upon the notification by the County Executive; and, be it further

RESOLVED, that the Chairman of the Ulster County Legislature be

authorized to execute all necessary agreements, certifications or reimbursement

requests for Federal Aid and/or applicable Marchiselli Aid on behalf of Ulster

County with the New York State Department of Transportation in connection with

the advancement or approval of the Project and providing for the administration of

the Project and the municipality’s first instance funding of Project costs and

permanent funding of the local share of federal-aid and state-aid eligible Project costs

and all Project costs within appropriations therefore that are not so eligible; and, be it

further

RESOLVED, that in addition to the Chairman of the Ulster County

Legislature, the following municipal titles: Commissioner of Public Works, County

Engineer, County Comptroller, and County Attorney are also hereby authorized to

execute any necessary Agreements or certifications on behalf of the Municipality

with NYSDOT in connection with the advancement or approval of the Project

identified in the State/Local Agreement; and, be it further

RESOLVED, that a certified copy of this resolution be filed with the New

York State Commissioner of Transportation by attaching it to any necessary

Agreement in connection with the Project; and, be it further

 

RESOLVED, that the 2018 Ulster County Capital Fund Budget is hereby

amended as follows:

 INCREASE AMOUNT

HH.5197.0507-4300.4355 Engineer Services $10,000.00

(App. #) Capital Project No. 507

 Horsenden Pavement Overlay (TIP)

HH.5197.0507-3500.5710 Revenue – Serial Bonds $10,000.00

(Rev. #s)

and move its adoption.

ADOPTED BY THE FOLLOWING VOTE:

AYES: 21 NOES: 0

(Legislator Petit arrived at 8:53 PM)

(Absent: Legislator Fabiano)

Passed Committee: Public Works and Capital Projects on September 5, 2018

Passed Committee: Ways and Means on September 12, 2018

FINANCIAL IMPACT:

$10,000.00 – CAPITAL PROJECT NO. 507 ADDITIONAL APPROPRIATION

DOLLARS

$10,000.00 – SERIAL BOND PROCEEDS

 

STATE OF NEW YORK

 ss:

COUNTY OF ULSTER

I, the undersigned Clerk of the Legislature of the County of Ulster, hereby certify that the foregoing resolution is

the original resolution adopted by the Ulster County Legislature on the 20th Day of September in the year Two Thousand

and Eighteen, and said resolution shall remain on file in the office of said clerk.

IN WITNESS WHEREOF, I have hereunto set my hand and seal of the County of Ulster this 21st Day of

September in the year Two Thousand and Eighteen.

|s| Victoria A. Fabella

Victoria A. Fabella, Clerk

Ulster County Legislature

Submitted to the County Executive this Approved by the County Executive this

24th Day of September, 2018. 1st Day of October, 2018.

|s| Victoria A. Fabella |s| Michael P. Hein

Victoria A. Fabella, Clerk Michael P. Hein, County Executive

Ulster County Legislature

Current Text: PDF

Sponsors: 

 

Updated: February 4, 2019