Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works and Capital Projects Committee (Chairman Fabiano
and Legislators Greene, Litts, Nolan, and Roberts), and The Ways and Means
Committee (Chairman Gerentine and Legislators Archer, Bartels, Lopez, Maio,
James Maloney, Joseph Maloney, and Petit)
Chairman of the Public Works and Capital Projects Committee, Dean J. Fabiano,
offers the following:
WHEREAS, this resolution has been submitted by the County Executive on
behalf of the Department of Public Works – (Highways & Bridges); and
WHEREAS, a project for Wolven Bridge Replacement on Zena Road, in the
Town of Woodstock, PIN 8761.76 may be eligible for funding under Title 23 U.S.
Code, as amended, that calls for the apportionment of the costs of such program to be
borne at the ration of 80% federal funds 20% non-federal funds; and
WHEREAS, Capital Project No. 505 was established pursuant to Resolution
No. 305, dated July 18, 2017, in an amount of $191,000 to provide authorization and
funding for preliminary engineering and right-of-way incidental work at $191,000 for
the Project; and
WHEREAS, Resolution No. 142 dated April 17, 2018 amended such capital
project for the additional preliminary engineering, Right-of-Way Work and
Construction Inspection for the Project in the amount of $83,409.00, of which such
costs may be reimbursable up to 80% with federal funds, bringing the total project
cost to $274,409.00; and
WHEREAS, due to the scope of such projects, it is now necessary to increase
the total cost of Capital Project No. 505 – Wolven Bridge, to fund anticipated
additional engineering costs due to additional in house work in the scoping phase of
the projects; and
WHEREAS, the project was approved by the Ulster County Transportation
Council in the 2018-2022 Transportation Improvement Program; and
WHEREAS, the County desires to advance the Project by making a
commitment of 100% of the non-federal share of the additional preliminary
engineering work; now
THEREFORE, the Ulster County Legislature, duly convened, it is hereby
RESOLVED, that the Ulster County Legislature hereby authorizes Ulster
County to pay in the first instance 100% of the federal and non-federal share of the
cost of engineering work for the Project or portions thereof; and, be it further
RESOLVED, that, as funded, the Project is a Type II Action as defined under
6 NYCRR 617.5(c) (18) and does not require any determination or procedure under
the State Environmental Quality Review Act (SEQRA) and, be it further
RESOLVED, that the Ulster County Legislature has determined, after review
of the criteria contained in 6 NYCRR Parts 617.4 and 617.5, that the construction of
the project will constitute an Unlisted Action; and the County will conduct a
coordinated review and circulate its Notice of Intent to serve as Lead Agency,
together with the EAF and accompanying documentation to all interested and
involved agencies pursuant to 6 NYCRR Part 617.6(b) (2) (i) and
6 NYCRR Part 617.6(b) (3); and, be it further
RESOLVED, that in the event the full federal and non-federal share costs of
the Project exceeds the amount appropriated above, the Ulster County Legislature
shall convene as soon as possible to appropriate said excess amount immediately
upon the notification by the County Executive; and, be it further
RESOLVED, that the Chairman of the Ulster County Legislature be
authorized to execute all necessary agreements, certifications or reimbursement
requests for Federal Aid and/or applicable Marchiselli Aid on behalf of Ulster
County with the New York State Department of Transportation in connection with
the advancement or approval of the Project and providing for the administration of
the Project and the municipality’s first instance funding of Project costs and
permanent funding of the local share of federal-aid and state-aid eligible Project costs
and all Project costs within appropriations therefore that are not so eligible; and, be it
further
RESOLVED, that in addition to the Chairman of the Ulster County
Legislature, the following municipal titles: Commissioner of Public Works, County
Engineer, County Comptroller, and County Attorney are also hereby authorized to
execute any necessary Agreements or certifications on behalf of the Municipality
with NYSDOT in connection with the advancement or approval of the Project
identified in the State/Local Agreement; and, be it further
RESOLVED, that a certified copy of this resolution be filed with the New
York State Commissioner of Transportation by attaching it to any necessary
Agreement in connection with the Project; and, be it further
RESOLVED, that the 2018 Ulster County Capital Fund Budget is hereby
amended as follows:
INCREASE AMOUNT
HH.5197.0505-4300.4355 Engineer Services $10,000.00
(App. #) Capital Project No. 505
Wolven Br. Replacement (TIP)
HH.5197.0505-3500.5710 Revenue – Serial Bonds $10,000.00
(Rev. #s)
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: 21 NOES: 0
(Legislator Petit arrived at 8:53 PM)
(Absent: Legislator Fabiano)
Passed Committee: Public Works and Capital Projects on September 5, 2018
Passed Committee: Ways and Means on September 12, 2018
FINANCIAL IMPACT:
$10,000.00 – CAPITAL PROJECT NO. 505 ADDITIONAL APPROPRIATION
DOLLARS
$10,000.00 – SERIAL BOND PROCEEDS
STATE OF NEW YORK
ss:
COUNTY OF ULSTER
I, the undersigned Clerk of the Legislature of the County of Ulster, hereby certify that the foregoing resolution is
the original resolution adopted by the Ulster County Legislature on the 20th Day of September in the year Two Thousand
and Eighteen, and said resolution shall remain on file in the office of said clerk.
IN WITNESS WHEREOF, I have hereunto set my hand and seal of the County of Ulster this 21st Day of
September in the year Two Thousand and Eighteen.
|s| Victoria A. Fabella
Victoria A. Fabella, Clerk
Ulster County Legislature
Submitted to the County Executive this Approved by the County Executive this
24th Day of September, 2018. 1st Day of October, 2018.
|s| Victoria A. Fabella |s| Michael P. Hein
Victoria A. Fabella, Clerk Michael P. Hein, County Executive
Ulster County Legislature
Current Text: PDF
Updated: February 4, 2019
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 370
Committee Vote to Adopt Resolution No. 370
Committee Vote to Adopt Resolution No. 370
...