Resolution No. 48

Amending The 2020-2025 Capital Improvement Program – Establishing Capital Project No. 560 – DPW Large Culvert Inspections – Amending The 2020 Capital Fund Budget – Department Of Public Works

Resolution Information

Status: 
Adopted

RESOLUTION TEXT +-

Print

Referred to: The Public Works and Capital Projects Committee (Chairman Fabiano and Legislators Cahill, Greene, Heppner, and Litts), and The Ways and Means Committee (Chairwoman Archer and Legislators Bartels, Gavaris, Haynes, Maio, Ronk, and Walter)

 

Chairman of the Public Works and Capital Projects Committee, Dean J. Fabiano, and Deputy Chair Manna Jo Greene offer the following:

 

WHEREAS, this resolution has been submitted by the County Executive on behalf of the Department of Public Works (Highways & Bridges); and

 

WHEREAS, the Ulster County’s inventory lists 152 large culverts which have spans between 5ft and 20ft; and

 

WHEREAS, in order to determine the condition of the culverts and prioritize culvert infrastructure repairs it is essential that a condition rating be performed and the Commissioner of Public Works requests funds for inspection and evaluation to rate Ulster County’s large culvert inventory; and

 

WHEREAS, Ulster County Department of Public Works intends to contract with an outside agency for the inspection and evaluation of its culverts; and

 

WHEREAS, based upon examination by the Ulster County Legislature, the County’s funding of this Project constitutes a Type II action as defined under Sections 4.5.5 of the County of Ulster’s State Environmental Quality Review Act (SEQRA) Type II List, which was adopted pursuant to Resolution No. 118 dated April 20, 2010, and

 

            WHEREAS, Ulster County has determined that this funding action does not pose a significant potential environmental impact and may be progressed as a Type II action in accordance with 6 NYCRR Part 617 of SEQRA, and does not require any further determination or procedure under SEQRA; and

 

            WHEREAS, the Commissioner of Public Works requests that Capital Project No. 560 be established and funded in the amount of $48,000.00; now, therefore, be it

 

RESOLVED, that the 2020 - 2025 Ulster County Capital Improvement Program is amended as follows:

 

                                   

 

ADD                                                                  AMOUNT

 

DPW Large Culvert Inspections                     $48,000.00

 

and be it further,

 

RESOLVED, that Capital Project No. 560 is hereby established as follows:

 

                                                   CREATE                                                        AMOUNT

 

Capital Project No. 560           DPW Large Culvert Inspections                    $48,000.00

 

and be it further,

 

            RESOLVED, the 2020 Ulster County Capital Fund Budget is hereby amended as follows:

                                                       INCREASE                                         AMOUNT

 

HH.5197.0560.4300.4505              Professional Services                            $48,000.00

(App. #)                                            

 

HH.5197.0560.3500.5710              Serial Bonds                                            $48,000.00

(Rev. #)

 

and moves its adoption.

ADOPTED BY THE FOLLOWING VOTE:

 

AYES:                        NOES:    

 

Passed Committee:  Public Works and Capital Projects on ______________.

 

Passed Committee:  Ways and Means on ______________.

 

FINANCIAL IMPACT:

$48,000.00 – COUNTY CAPITAL FUND APPROPRIATIONS

$48,000.00 – COUNTY REVENUE - SERIAL BONDS

 

***A BOND RESOLUTION WILL BE REQUIRED***

Current Text: PDF

 

Updated: June 2, 2020

Votes on this Resolution

yes no abstained no vote
Tue, Feb 11, 2020 2020-2021 Term: Ways and Means Committee
Committee Vote to Adopt Resolution No. 48
-+
No
Abstained
No Vote
Wed, Feb 5, 2020 2020-2021 Term: Public Works and Capital Projects Committee
Committee Vote to Adopt Resolution No. 48
-+
No
Abstained
No Vote

...