Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works and Capital Projects Committee (Chairman Fabiano
and Legislators Archer, Greene, Loughran and Roberts), and The Ways and Means
Committee (Chairman Gerentine and Legislators Allen, Belfiglio, Briggs, Gregorius,
Maio, Maloney and R. Parete)
Chairman of the Public Works and Capital Projects Committee, Dean J. Fabiano, and
Deputy Chairman Peter M. Loughran offer the following:
WHEREAS, this resolution has been submitted by the County Executive on
behalf of the Department of Public Works; and
WHEREAS, the County Executive has established an Infrastructure
Investment Program known as “Building a Better Ulster County” to begin addressing
critical road and bridge improvements at the County level; and
WHEREAS, Resolution No. 62 of February 17, 2015 established Capital
Project No. 445 for the Rehabilitation of the Leggs Mill Bridge in the amount of
$562,500.00; and
WHEREAS, the bid for construction costs for Capital Project No. 445 are
estimated to be an additional $65,000.00; and
WHEREAS, the Commissioner of Public Works requests that the 2015 – 2020
Capital Program be amended to increase the project by $65,000.00 in order to
accomplish the rehabilitation; and
WHEREAS, based upon examination by the Ulster County Legislature, the
County’s funding of this Project constitutes a Type II action as defined under
Sections 4.5.5 of the County of Ulster’s State Environmental Quality Review Act
(SEQRA) Type II List, which was adopted pursuant to Resolution No. 118, April 20,
2010; and
WHEREAS, Ulster County has determined that this funding action does not
pose a significant potential environmental impact and may be progressed as a Type II
action in accordance with 6 NYCRR Part 617 of SEQRA, and does not require any
further determination or procedure under SEQRA; now, therefore, be it
RESOLVED, that the 2015 – 2020 Capital Program be amended to increase
Capital Project No. 445 – “Building a Better Ulster County” Infrastructure
Investment Program – Rehabilitation of the Leggs Mill Bridge from $562,500.00 to
$627,500.00 to include the increase in construction costs; and be it further
RESOLVED, that the 2015 Capital Fund Budget be amended as follows:
INCREASE AMOUNT
HH.5197.0445-2300.2550 Construction $65,000.00
(Appr. #) Leggs Mill Bridge #152
Town of Ulster
HH.5197.0445-3500.5710 Serial Bonds $65,000.00
(Rev. #)
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: 21 NOES: 0
(Legislator R. Parete arrived at 7:21 PM)
(Absent: Legislator Ronk)
Passed Committee: Public Works and Capital Projects on November 5, 2015
Passed Committee: Ways and Means on November 10, 2015
FINANCIAL IMPACT:
$65,000.00 – ADDITIONAL CAPITAL FUND APPROPRIATIONS
$65,000.00 – ADDITIONAL REVENUES – SERIAL BONDS-COUNTY
STATE OF NEW YORK
ss:
COUNTY OF ULSTER
I, the undersigned Clerk of the Legislature of the County of Ulster, hereby certify that the foregoing resolution is
the original resolution adopted by the Ulster County Legislature on the 17th Day of November in the year Two Thousand
and Fifteen, and said resolution shall remain on file in the office of said clerk.
IN WITNESS WHEREOF, I have hereunto set my hand and seal of the County of Ulster this 19th Day of
November in the year Two Thousand and Fifteen.
|s| Victoria A. Fabella
Victoria A. Fabella, Clerk
Ulster County Legislature
Submitted to the County Executive this Approved by the County Executive this
19th Day of November, 2015. 24
th Day of November, 2015.
|s| Victoria A. Fabella |s| Michael P. Hein
Victoria A. Fabella, Clerk Michael P. Hein, County Executive
Ulster County Legislature
Current Text: PDF
Updated: October 27, 2020
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 435
Committee Vote to Adopt Resolution No. 435
Committee Vote to Adopt Resolution No. 435
Committee Vote to Adopt Resolution No. 435