Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works and Capital Projects Committee (Chairman Fabiano
and Legislators Allen, Greene, Loughran and Roberts), and The Ways and Means
Committee (Chairman Gerentine and Legislators Bartels, Belfiglio, Briggs, Maio,
Maloney, Provenzano, and Rodriguez)
Chairman of the Public Works and Capital Projects Committee, Dean J. Fabiano, and
Deputy Chairman Peter M. Loughran offer the following:
WHEREAS, this Resolution has been submitted by the County Executive on
behalf of the Department of Public Works; and
WHEREAS, the project expenditures in the amount of $550,000.00 for the
Fleet Service Bay Expansion, were approved in the 2014 – 2019 Capital Program;
and
WHEREAS, the project will renovate existing space at the DPW Quarry
complex in order to provide additional mechanics’ bays for Central Garage
operation; and
WHEREAS, this renovation of an existing structure constitutes a Type II
action under section 2.2 of the County of Ulster’s State Environmental Quality
Review Act (SEQRA) Type II List that was adopted by Resolution No. 118 on April
20, 2010; and
WHEREAS, as per section 3 of the County’s Type II List, this action does not
pose a significant potential environmental impact and may be progressed as a Type II
action in accordance with 6 NYCRR Part 617 of SEQRA; and
WHEREAS, the Commissioner of Public Works requests that Capital Project
No. 403 be established and funded; now, therefore, be it
RESOLVED, that Capital Project No. 403 be established for the expansion of
the fleet service bay; and, be it further
RESOLVED, that the 2014 Ulster County Capital Fund is hereby amended as
follows:
- Page 2 -
Resolution No. 85 March 18, 2014
Establishing Capital Project No. 403 – Fleet Service Bay Expansion
– Department Of Public Works (Buildings & Grounds)
INCREASE AMOUNT
H4-0403-2962 Engineering Services $60,000.00
(App. #)
H4-0403-2911 Construction $490,000.00
H3-0403-5710 Revenue - Serial Bonds $550,000.00
(Rev. #)
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: 23 NOES: 0
Passed Committee: Public Works & Capital Projects on March 6, 2014
Passed Committee: Ways & Means on March 12, 2014
FINANCIAL IMPACT:
$550,000.00 – COUNTY FUNDS – SERIAL BONDS
- Page 3 -
Resolution No. 85 March 18, 2014
Establishing Capital Project No. 403 – Fleet Service Bay Expansion
– Department Of Public Works (Buildings & Grounds)
STATE OF NEW YORK
ss:
COUNTY OF ULSTER
This is to certify that I, the undersigned Clerk of the Legislature of the County of Ulster have compared the
foregoing resolution with the original resolution now on file in the office of said clerk, and which was adopted by said
Legislature on the 18th Day of March, 2014, and that the same is a true and correct transcript of said resolution and of the
whole thereof.
IN WITNESS WHEREOF, I have hereunto set my hand and seal of the County of Ulster this 20th Day of March
in the year Two Thousand and Fourteen.
|s| Victoria A. Fabella
Victoria A. Fabella, Clerk
Ulster County Legislature
Submitted to the County Executive this Approved by the County Executive this
20th Day of March, 2014. 24th Day of March, 2014.
|s| Victoria A. Fabella |s| Michael P. Hein
Victoria A. Fabella, Clerk Michael P. Hein, County Executive
Ulster County Legislature
Current Text: PDF
Updated: October 27, 2020
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 85
Committee Vote to Adopt Resolution No. 85
Committee Vote to Adopt Resolution No. 85
Committee Vote to Adopt Resolution No. 85