Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works, Capital Projects and Transportation Committee (Chairwoman Petit and Legislators Erner, Fabiano, Litts, and Nolan), and The Ways and Means Committee (Chairman Gavaris and Legislators Cahill, Roberts, Ronk, and Walter)
Chairwoman of the Public Works, Capital Projects and Transportation Committee, Laura Petit, and Deputy Chair Dean J. Fabiano, offer the following:
WHEREAS, this resolution has been submitted at the request of the County Executive on behalf of the Department of Public Works; and
WHEREAS, the superstructure of a bridge is a primary structural element for all bridges; and
WHEREAS a bridge preservation approach to make repairs to the bridge superstructure will extend the life of the bridge; and
WHEREAS, the Commissioner of Public Works has identified five bridges for the 2023 Bridge Superstructure Repairs project; and
WHEREAS, the Ulster County Commissioner of Public Works requests funds for evaluation and designof the Watson Hollow Bridge in the Town of Olive (BIN 3346370), High Falls Bridge in the Town of Denning (BIN 3025130), Coxing Bridge in the Town of Rosendale (BIN 3347040) Saugerties Reservoir Bridge in the Town of Saugerties (BIN 3347790) and Tuttletown Bridge in the Town of Gardiner (BIN 3346640); and
WHEREAS the Ulster County Department of Public Works intends to contract with an outside agency for the evaluation and design of superstructure repairs for the bridges; and
WHEREAS, based upon examination by the Ulster County Legislature, the County’s funding of this Project constitutes a Type II action as defined under Section 4.5.5 of the County of Ulster’s State Environmental Quality Review Act (SEQRA) Type II List, which was adopted pursuant to Resolution No. 118 dated April 20, 2010; and
WHEREAS, Ulster County has determined that this funding action does not pose a significant potential environmental impact and may be progressed as a Type II action in accordance with 6 NYCRR Part 617 of SEQRA, and does not require any further determination or procedure under SEQRA; and
WHEREAS the Commissioner of Public Works requests that Capital Project No. 661 be established to fund design services in the amount of $65,000.00; and
WHEREAS the Commissioner of Public Works requests that Capital Project No. 661 be established for the evaluation and design of superstructure repairs, and include construction inspection services during the construction phase at a later date; now, therefore be it
RESOLVED, that the 2023-2028 Ulster County Capital Improvement Program is amended as follows:
INCREASE AMOUNT
Capital Project No. 661 Bridge Superstructure Repairs $65,000.00
and, be it further
RESOLVED, that Capital Project No. 661 – Bridge Superstructure Repairs is hereby established as follows:
CREATE AMOUNT
Capital Project No. 661 Bridge Superstructure Repairs $65,000.00
and, be it further
RESOLVED, that the 2021 Ulster County Capital Fund is hereby amended as follows:
INCREASE AMOUNT
HH.5197.0661-4300.4505 Professional Services $65,000.00
(App. #)
HH.5197.0661-3500.5710 Serial Bonds $65,000.00
(Rev. #),
and moves its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: NOES:
Passed Committee: Public Works, Capital Projects and Transportation on ______________.
Passed Committee: Ways and Means on ______________.
FINANCIAL IMPACT:
$65,000.00 – CAPITAL FUND APPROPRIATIONS
$65,000.00 – COUNTY REVENUE - SERIAL BONDS
***A BOND RESOLULTION WILL BE REQUIRED***
Current Text: PDF
Updated: June 21, 2023
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 192
Committee Vote to Adopt Resolution No. 192
Committee Vote to Adopt Resolution No. 192 As Amended
...