Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works and Capital Projects Committee (Chairwoman Petit and Legislators Fabiano, Greene, Litts, and Nolan), The Legislative Programs, Education and Community Services Committee (Chairman Delaune and Legislators Collins, Donaldson, Haynes, and Wawro), and The Ways and Means Committee (Chairwoman Archer and Legislators Gerentine, Maio, James Maloney, Joseph Maloney, Petit, and Rodriguez)
Chairman of the Legislative Programs, Education and Community Services Committee, James Delaune, and Deputy Chair Heidi Haynes, offer the following:
WHEREAS, this resolution has been submitted by the County Executive on behalf of SUNY Ulster; and
WHEREAS, the 2019-2024 Capital Improvement Program includes the Roof Replacement and Exterior Site Work project, totaling $10,382,625.00; and
WHEREAS, Resolution No. 547, dated December 20, 2016 approved the establishment and funding of Capital Project No. 489 SUNY Ulster - Dewitt Library Roof Replacement (PHASE 1 of Campus Roofs Project) in the amount of $250,000.00; and
WHEREAS, Resolution No. 111, dated March 20, 2018, amended Resolution No. 547 that established Capital Project No. 489 SUNY Ulster - Dewitt Library Roof Replacement – to change the scope of such Capital Project to include roof assessments and design services for various buildings - SUNY Ulster; and
WHEREAS, Resolution No. 259 dated June 19, 2018, authorized the Chairman of The Ulster County Legislature to Enter into an agreement with the New York State Dormitory Authority Of The State of New York (“DASNY”) for project management services – Ulster County Community College; and
WHEREAS, Resolution No. 463 dated November 20, 2018, approved the Work Order Number 2019-003 totaling $116,000.00 (inclusive of DASNY in-house design fee of $116,000) for in-house design services to design roof replacements for John Vanderlyn Hall Skylight, MacDonald Dewitt Library and Burroughs Hall (minus Lecture Hall); and
WHEREAS, Resolution No. 147 dated April 16, 2019, approved the Work Order Number 2019-005 totaling $1,407,000.00 (inclusive of DASNY Construction Fee of $97,000.00) for construction phase services related to roof replacements of John Vanderlyn Hall Skylight, MacDonald Dewitt Library and Burroughs Hall (minus Lecture Hall); and
WHEREAS, SUNY Ulster and the County are now formally requesting design and construction phase services for PHASE 2 of Campus Roofs Project for Hardenburgh Hall from DASNY; and
WHEREAS, the SUNY Ulster Board of Trustees approved the Work Order Number 2019-009 via resolution #19-6-127, at the Board of Trustees meeting held on June 18, 2019; and
WHEREAS, such Work Order totals $1,600,000.00 (inclusive of DASNY Design Fee of $104,500.00 and DASNY Construction Fee of $140,000.00) which will be divided as follows: $800,000.00 State and $800,000.00 Ulster County; now, therefore, be it
RESOLVED, that the Ulster County Legislature hereby approves the Work Order - Design and Construction Phase Services for Phase 2 of Campus Roofs Project – Hardenburgh Hall with DASNY related to the Campus Roofs Capital Project No. 489 – Campus Roofs - SUNY Ulster; and, be it further
RESOLVED, that the 2019-2024 Ulster County Capital Fund Budget is hereby amended as follows:
INCREASE AMOUNT
HH.2497.0489-2300.2550 Other Equipment & $1,355,500.00
(App. #) Capital Outlays Construction
HH.2497.0489-4300.4300 Professional Services Architectural $ 244,500.00
(App. #)
HH.2497.0489-3300.3297 Revenue – State Aid $ 800,000.00
(Rev. #)
INCREASE AMOUNT
HH.2497.0489-3500.5710 Revenue – Serial Bonds $ 800,000.00
(Rev. #)
Current Text: PDF
Updated: August 21, 2019
Votes on this Resolution
yes no abstained no voteCommittee Vote to Adopt Resolution No. 302
Vote to Adopt Resolution No. 302
Committee Vote to Postpone Resolution No. 302 For One Week
Committee Vote to Adopt Resolution No. 302
Committee Vote to Adopt Resolution No. 302
...