Resolution No. 250

Approving The Work Order With The Dormitory Authority Of The State Of New York (DASNY) To Provide Design And Construction Management Services For The Installation Of An Accessible Ramp At The Burroughs Lecture Hall, Related To The Capital Project No. 524 SUNY Ulster – Burroughs Renovations– SUNY Ulster

Resolution Information

Status: 
Adopted

RESOLUTION TEXT +-

Print

Referred to: The Public Works and Capital Projects Committee (Chairwoman Petit and Legislators Fabiano, Greene, Litts, and Nolan), The Legislative Programs, Education and Community Services Committee (Chairman Delaune and Legislators Collins, Donaldson, Haynes, and Wawro), and The Ways and Means Committee (Chairwoman Archer and Legislators Gerentine, Maio, James Maloney, Joseph Maloney, Petit, and Rodriguez)

 

Chairman of the Legislative Programs, Education and Community Services Committee, James Delaune, and Deputy Chair Heidi Haynes, offer the following:

 

WHEREAS, this resolution has been submitted by the Acting County Executive on behalf of SUNY Ulster; and

 

WHEREAS, the Chair of the Ulster County Legislature approved the Program Management agreement with the Dormitory Authority of New York State for the provision of project management services via Resolution No. 259 at the Regular Legislative Session held on June 19, 2018; and

 

WHEREAS, Resolution No. 112, dated March 20, 2018, established Capital Project No. 524 SUNY Ulster – Burroughs Renovations and amended 2018 Capital Improvement to Plan to add such project and fund such project in the amount of $552,200.00; and

 

WHEREAS, in accordance with the Americans with Disabilities Act (ADA) standards, Burroughs Lecture Hall is in a need of a handicapped accessible ramp to ensure access to all levels of the Lecture Hall; and

 

WHEREAS, the SUNY Ulster Board of Trustees approved the Work Order No. 2019-008 with the Dormitory Authority of the State of New York (DASNY) (Capital Project: Burroughs Renovations) via resolution #19-5-114, at the Board of Trustees meeting held on May 21, 2019; and

 

WHEREAS, such Work Order totals $61,500.00 (inclusive of DASNY Fee of $19,800.00) for such project, which will be divided as follows: $30,750.00 State and $30,750.00 Ulster County; now, therefore be it

 

 

 

 

RESOLVED, that Chair of the Ulster County Legislature is hereby authorized to execute Work Order No. 2019-008 – Installation of An Accessible Ramp at Burroughs Lecture Hall with DASNY for the provision of design and construction management services,

 

and move its adoption.

 

 

ADOPTED BY THE FOLLOWING VOTE:

 

AYES:                        NOES:    

 

 

Passed Committee: Public Works and Capital Projects on ______________.

 

Passed Committee: Legislative Programs, Education and Community Services on __.

 

Passed Committee: Ways and Means on _____________.

 

 

FINANCIAL IMPACT:

$61,500 – BUDGETED CAPITAL PROJECT NO. 524 APPROPRATIONS (50%

 REIMBURSABLE FROM NEW YORK STATE DORMITORY    

 AUTHORITY)   

$61,500 – BUDGETED CAPITAL PROJECT NO. 524 SERIAL BONDS

                  PREVIOUSLY AUTHORIZED          

Current Text: PDF

 