Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works and Capital Projects Committee (Chairman Fabiano
and Legislators Archer, Greene, Loughran, and Roberts), and The Ways and Means
Committee (Chairman Gerentine and Legislators Allen, Belfiglio, Briggs, Gregorius,
Maio, Maloney, and Richard Parete)
Chairman of the Public Works and Capital Projects Committee, Dean J. Fabiano, and
Deputy Chairman Peter M. Loughran offer the following:
WHEREAS, this resolution has been submitted by the County Executive on
behalf of the Department of Public Works; and
WHEREAS, the Commissioner of Public Works has prepared a list of various
Ulster County buildings in need of HVAC/Weatherization replacement/upgrade; and
WHEREAS, the project will increase operational efficiencies, energy
conservation and improve ventilation where required; and
WHEREAS, project expenditures in the amount of $2,500,000.00 for
HVAC/Weatherization Project – Various County Buildings, were approved in the
2015 – 2020 Capital Program; and
WHEREAS, it may be necessary for the Commissioner of Finance to transfer
funds between these projects when bids are opened; and
WHEREAS, the Commissioner of Public Works requests that Capital Project
Nos. 392 through 402 be established and funded in a total amount of $2,500,000.00
in order to provide HVAC/Weatherization replacements/upgrades to various County
buildings; and, now, therefore, be it
RESOLVED, that Capital Project Nos. 392 through 402 for
HVAC/Weatherization Projects are hereby established as follows:
CREATE
Capital Project No. 392
UC Courthouse – HVAC Weatherization
Capital Project No. 393
UC Office Complex (Ulster Avenue) – HVAC Weatherization
Capital Project No. 394
UC Office Building – HVAC Weatherization
Capital Project No. 395
UC Mental Health Building – HVAC Weatherization
Capital Project No. 396
UC Records Storage – HVAC Weatherization
Capital Project No. 397
Trudy Resnick Farber Building – HVAC Weatherization
Capital Project No. 398
Carr Building – HVAC Weatherization
Capital Project No. 399
UC DPW Building- HVAC Weatherization
Capital Project No. 400
UC Probation Office – HVAC Weatherization
Capital Project No. 401
Welding Shop – DPW Quarry Complex – HVAC Weatherization
Capital Project No. 402
Mechanics Complex – DPW Quarry – HVAC Weatherization
INCREASE AMOUNT
Capital Project No. 392
HH.1997.0392-4300.4355 Professional Services-Engineering $ 107,220.00
(App. #)
HH.1997.0392-2300.2550 Construction $ 893,500.00
(App. #)
HH.1997.0392-3500.5719 Revenue - Serial Bonds $1,000,720.00
(Rev. #)
Capital Project No. 393
HH.1997.0393-4300.4355 Professional Services-Engineering $ 39,600.00
(App. #)
HH.1997.0393-2300.2550 Construction $ 330,000.00
(App. #)
HH.1997.0393-3500.5719 Revenue - Serial Bonds $ 369,600.00
(Rev. #)
Capital Project No. 394
HH.1197.0394-4300.4355 Professional Services-Engineering $ 36,835.00
HH.1997.0394-2300.2550 Construction $ 309,500.00
(App. #)
HH.1997.0394-3500.5719 Revenue - Serial Bonds $ 346,335.00
(Rev. #)
Capital Project No. 395
HH.1997.0395-4300.4355 Professional Services-Engineering $ 13,200.00
(App. #)
HH.1997.0395-2300.2550 Construction $ 110,000.00
(App. #)
HH.1997.0395-3500.5719 Revenue - Serial Bonds $ 123,200.00
(Rev. #)
Capital Project No. 396
HH.1997.0396-4300.4355 Professional Services-Engineering $ 7,440.00
(App. #)
HH.1997.0396-2300.2550 Construction $ 62,000.00
(App. #)
HH.1997.0396-3500.5719 Revenue - Serial Bonds $ 69,440.00
(Rev. #)
Capital Project No. 397
HH.1997.0397-4300.4355 Professional Services-Engineering $ 7,464.00
(App. #)
HH.1997.0397
Capital Project No. 399
HH.1997.0399-4300.4355 Professional Services-Engineering $ 7,337.00
(App. #)
HH.1997.0399-2300.2550 Construction $ 61,000.00
(App. #)
HH.1997.0399-3500.5719 Revenue - Serial Bonds $ 68,337.00
(Rev. #)
Capital Project No. 400
HH.1997.0400-4300.4355 Professional Services-Engineering $ 16,584.00
(App. #)
HH.1997.0400-2300.2550 Construction $ 138,200.00
(App. #)
HH.1997.0400-3500.5719 Revenue - Serial Bonds $ 154,784.00
(Rev. #)
Capital Project No. 401
HH.1997.0401-4300.4355 Professional Services-Engineering $ 8,640.00
(App. #)
HH.1997.0401-2300.2550 Construction $ 72,000.00
(App. #)
HH.1997.0401-3500.5719 Revenue - Serial Bonds $ 80,640.00
(Rev. #)
Capital Project No. 402
HH.1997.0402-4300.4355 Professional Services-Engineering $ 14,880.00
(App. #)
HH.1997.0402-2300.2550 Construction $ 124,000.00
(App. #)
HH.1997.0402-3500.5719 Revenue - Serial Bonds $ 138,880.00
(Rev. #)
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: 23 NOES: 0
Passed Committee: Public Works and Capital Projects on August 6, 2015
Passed Committee: Ways and Means on August 12, 2015
FINANCIAL IMPACT:
$2,500,000.00 – COUNTY FUNDS – SERIAL BONDS
STATE OF NEW YORK
ss:
COUNTY OF ULSTER
I, the undersigned Clerk of the Legislature of the County of Ulster, hereby certify that the foregoing resolution is
the original resolution adopted by the Ulster County Legislature on the 18th Day of August in the year Two Thousand and
Fifteen, and said resolution shall remain on file in the office of said clerk.
IN WITNESS WHEREOF, I have hereunto set my hand and seal of the County of Ulster this 19th Day of August
in the year Two Thousand and Fifteen.
|s| Victoria A. Fabella
Victoria A. Fabella, Clerk
Ulster County Legislature
Submitted to the County Executive this Approved by the County Executive this
20th Day of August, 2015. 26
th Day of August, 2015.
|s| Victoria A. Fabella |s| Michael P. Hein
Victoria A. Fabella, Clerk Michael P. Hein, County Executive
Ulster County Legislature
Current Text: PDF
Updated: October 27, 2020
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 316
Committee Vote to Adopt Resolution No. 316
Committee Vote to Adopt Resolution No. 316
Committee Vote to Adopt Resolution No. 316