Resolution Information
RESOLUTION TEXT +-
Referred to: The Public Works, Capital Projects and Transportation Committee (Chair Nolan and Legislators Donaldson, Kovacs, Litts, and McCollough), and The Ways and Means Committee (Chairman Gavaris and Legislators Collins, Hansut, Kovacs, Nolan, and Roberts)
Chair of the Public Works, Capital Projects and Transportation Committee, Kathy Nolan, Deputy Chair Herbert Litts, III, and Legislator Stewart offer the following:
WHEREAS, this resolution has been submitted at the request of the County Executive on behalf of the Department of Public Works; and
WHEREAS, the Beaverkill Road Bridge over Scudder Brook Replacement Project (PIN 8762.80) in the Town of Hardenburgh Ulster County; and
WHEREAS, this Locally Administered Federal Aid Project provides for the replacement of the Beaverkill Road Bridge due to extensive deterioration of the weathering steel girders and asphalt pan superstructure and the concrete substructures; and
WHEREAS, Capital Project No. 680 was established pursuant to Resolution No. 742 dated December 18, 2023, in the amount of $285,000.00 to provide authorization and funding for preliminary engineering and right-of-way incidental work for the Project; and
WHEREAS, an engineering consultant has been selected for the Project and a scope of services and cost proposal have been established; and
WHEREAS, based on information provided from such engineering consultant it has been determined that it is now necessary to increase the federal and non-federal share of costs for the engineering and right-of-way work for the Project by $40,386.00, of which such costs may be reimbursable up to 80% with federal funds, bringing the total phase of the project cost to $325,386.00; and
WHEREAS, the Commissioner of Public Works requests that Capital Project No 680 be amended and funded for a total project amount of $40,386.00 in order to provide engineering and right of way for a new total project amount totaling $325,386.00; now, therefore be it
RESOLVED, based upon examination by the Ulster County Legislature, the County’s funding of this Project constitutes a Type II action as defined under Section 4.5.6 of the County of Ulster’s State Environmental Quality Review Act (SEQRA) Type II List, which was adopted pursuant to Resolution No. 118 dated April 20, 2010; and, be it further
RESOLVED, Ulster County has determined that this funding action does not pose a significant potential environmental impact and may be progressed as a Type II action in accordance with 6 NYCRR Part 617 of SEQRA, and does not require any further determination or procedure under SEQRA; and, be it further
RESOLVED, that the 2024-2029 Ulster County Capital Improvement Program is amended as follows;
INCREASE AMOUNT
Capital Project No. 680 Scudder Brook Bridge $40,386.00
Replacement
and, be it further
RESOLVED, that Capital Project No. 680 for Scudder Brook Bridge Replacement is hereby amended as follows;
INCREASE AMOUNT
Capital Project No. 680 Scudder Brook Bridge $40,386.00
Replacement
and, be it further
RESOLVED, that the 2024 Ulster County Capital Fund budget is hereby amended as follows:
|
INCREASE
|
AMOUNT |
HH.5197.0680-4300.4505 (App.#) |
Professional Services
|
$40,386.00 |
|
|
|
HH.5197.0680-3500.5710 Revenue -Serial Bond $40,386.00
(Rev. #),
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: NOES:
Passed Committee: Public Works, Capital Projects and Transportation on __________.
Passed Committee: Ways and Means on __________.
FINANCIAL IMPACT:
$40,386.00 – COUNTY CAPITAL FUND APPROPRIATIONS
$40,386.00 – COUNTY REVENUE - SERIAL BONDS
*** A BOND RESOLUTION WILL BE REQUIRED ***
Current Text: PDF
Updated: May 29, 2024
Votes on this Resolution
yes no abstained no voteVote to Adopt Resolution No. 244
Committee Vote to Adopt Resolution No. 244
...