WHEREAS, this resolution has been submitted by the County Executive on behalf of the Department of Public Works; and
WHEREAS, the approved 2019-2024 Capital Improvement Program includes a project “Sundown Bridge” in the amount of $885,000.00 for the project; and
WHEREAS, the original project scope called for the rehabilitation of the existing trust superstructure in place; and
WHEREAS, based upon the current state of deterioration of the existing trusses, and the age of the structure, rehabilitation is no longer feasible based on the original scope; and
WHEREAS, Capital Project No. 390 was established pursuant to Resolution No. 104, dated April 16, 2013, to provide authorization and funding for preliminary engineering for the Project; and
WHEREAS, it was subsequently found necessary to undertake additional work not contemplated in the original project to provide a safely renovated bridge; and
WHEREAS, it has been found necessary to increase the funding of Capital Project No. 390 by $845,000.00 for the remaining work required; and
WHEREAS, the Commissioner of Public Works requests that Capital Project No. 390 be amended and funded in a total amount of $970,000.00; and
WHEREAS, based upon examination by the Ulster County Legislature, the County’s funding of this Project constitutes a Type II action as defined under Sections 4.5.5 of the County of Ulster’s State Environmental Quality Review Act (SEQRA) Type II List, which was adopted pursuant to Resolution No. 118 dated April 20, 2010; and
WHEREAS, Ulster County has determined that this funding action does not pose a significant potential environmental impact and may be progressed as a Type II action in accordance with 6 NYCRR Part 617 of SEQRA, and does not require any further determination or procedure under SEQRA; now, therefore, be it
RESOLVED, that the 2019 – 2024 Ulster County Capital Improvement Program is hereby amended as follows:
INCREASE AMOUNT
Sundown Bridge $85,000.00
and, be it further
RESOLVED, that the 2019 Capital Fund Budget is hereby amended as follows:
INCREASE AMOUNT
HH.5197.0390-4100.4100 Capital Project No. 390 $845,000.00
(App. #) Sundown Bridge
Town of Denning
Bridge Materials
HH.5197.0390-3500-5710 Revenue – Serial Bonds $845,000.00
(Rev. #)
and move its adoption.
ADOPTED BY THE FOLLOWING VOTE:
AYES: NOES:
Passed Committee: Public Works and Capital Projects on _____________.
Passed Committee: Ways and Means on ______________.
FINANCIAL IMPACT:
$845,000.00 – ADDITONAL 2019 CAPITAL APPROPRIATIONS
$845,000.00 – ADDITIONAL 2019 CAPITAL REVENUES – SERIAL BONDS
***A BOND RESOLUTION WILL BE REQUIRED***
Current Text: PDF
Updated: April 5, 2019
Votes on this Resolution
yes no abstained no voteCommittee Vote to Adopt Resolution No. 58
Committee Vote to Adopt Resolution No. 58
...